Construction Photos

BUILDING COMPLETE!! March 24, 2022

NEARING COMPLETION!! March 9, 2022

NEARING COMPLETION!! February 24, 2022

NEARING COMPLETION!! February 11, 2022

NEARING COMPLETION!! January 27, 2022

OFFICE CONSTRUCTION UNDERWAY!! January 18, 2022

ROOF INSTALLED!! December 6, 2021

WALLS TILTED!! October 6, 2021

Foundation Poured!! August 26, 2021

Pad Formed!! August 12, 2021

Grading Underway!! July 30, 2021

Grading Underway!! July 14, 2021

Demolition Nearing Completion!! June 9, 2021

Demolition Underway!! May 13, 2021